OSSF permit and site-evaluation fees and typical review timelines.

State rules are the floor. Figures here are TCEQ minimums under 30 TAC Chapter 285. Your county can be stricter and around here most are — check your county before you rely on a number.

Two different numbers, and they vary.

Permit fees are set by each county, not by the state, and they differ enough to matter. Hood County publishes $475 for a new residential system and $310 for a modification. Others differ, and several do not publish a schedule at all. Where we have verified a county's fees, they are on that county's page.

Site evaluation is a separate cost, paid to the licensed site evaluator or engineer rather than to the county.

On timeline, the number to plan against is 30 days for permit review — that is the rule. Design runs a few weeks ahead of that, and installation follows once the Authorization to Construct is issued.

Fees change, so check the county page and then confirm with the county before you write the cheque.

Reviewed August 2026. Links go to the sources this answer was checked against.