Spray field layout — required coverage area, keeping spray within property, landscaping and planting restrictions over the field.
State rules are the floor. Figures here are TCEQ minimums under 30 TAC Chapter 285. Your county can be stricter and around here most are — check your county before you rely on a number.
The spray field must be at least Q ÷ Ri square feet, on terrain sloping ≤15% (steeper only if landscaped and terraced to stop runoff), covered with grasses, evergreen shrubs, bushes, trees or landscaped beds of mixed vegetation, with nothing within 10 feet of a sprinkler that would interfere with uniform application; overlapping circular patterns may be used but overlapped area counts only once (TCEQ RG-472, §285.33(d)(2)). Spray is prohibited on land used for growing food, gardens, orchards, crops for human consumption, and unseeded bare ground — bare areas must be seeded or sodded and growing before start-up, and every application must include a landscape plan detailing the vegetation to be maintained (TCEQ RG-472; TCEQ, Choosing a Septic System). Containment is enforced through the Table X edge-of-spray setbacks (20 ft to property lines, 10 ft with a commercial timer spraying midnight–5:00 a.m.), low-angle nozzles with a trajectory of 15 degrees or less, maximum 40 psi sprinkler inlet pressure, rates adjusted so there is no runoff, purple-colored distribution components, buried piping with no hose bibs, and storage of one day's flow (timer systems) or a dosing volume of half the daily flow (non-timer) (TCEQ RG-472). Hays County adds a 15-ft sprinkler setback from trees 24 inches or greater in diameter, a maximum sprinkler operating height of 24 inches, and prohibits spray for commercial/institutional flows over 300 gpd (Hays County OSSF Regulations).
Reviewed August 2026. Links go to the sources this answer was checked against.
More on design & engineering
- What a site evaluation is and what the evaluator actually tests and documents.
- Soil profile analysis vs percolation test — which Texas requires, when each is allowed, how each is performed under 30 TAC 285.
- How design loading rate translates into drainfield square footage or spray-area size.
- When a Professional Engineer's seal is required on the design instead of a site evaluator's or installer's plan.
- Designing around hard site limits: shallow bedrock, high water table, steep slope, restrictive horizon, tight lot.
- Setback and separation distances under 30 TAC 285.91(10) — actual table numbers.