How long does it take from application to final inspection?
State rules are the floor. Figures here are TCEQ minimums under 30 TAC Chapter 285. Your county can be stricter and around here most are — check your county before you rely on a number.

There is no single number, because three separate clocks run in sequence and only one of them is fixed by rule.
Design typically takes a few weeks, depending on your site evaluator's schedule and how complex the site is.
**Permit review is the one with a rule behind it: the permitting authority must approve or deny within 30 days of receiving a complete application.** Thirty days is the right number for planning purposes. Larger or non-standard systems may also go to TCEQ after the county review, which adds time.
Installation then depends on your installer's availability and the weather, plus the inspection itself, which has to be scheduled.
Plan the whole thing generously and start early. Almost every delay we see traces back to someone setting a move-in date before the site evaluation was booked.
Reviewed August 2026. Links go to the sources this answer was checked against.
More on installation
- What is the full step-by-step process to install a new septic system in Texas?
- Can a homeowner legally install their own septic system in Texas?
- What does the installer or site evaluator need from me before breaking ground?
- Who provides electrical service to the septic area for an aerobic system, and what's required?
- What actually happens on install day — access, clearing, spoils, yard damage?
- On new construction, does the septic go in before or after the house/slab?