On new construction, does the septic go in before or after the house/slab?

State rules are the floor. Figures here are TCEQ minimums under 30 TAC Chapter 285. Your county can be stricter and around here most are — check your county before you rely on a number.

There is no rule about this. It is a scheduling decision, and the right answer depends on your site.

Our preference is to put the system in at the very end of the job, after the house is finished. The reason is traffic and grading. Every trade on site drives across the lot, and driving over a drainfield or a spray field damages it. On a drip system, grading changes late in the job can undo what was designed. Going last avoids both.

Sometimes you cannot. On a tight lot, or where the disposal area sits behind the house, the only window to get a truck back there is before the house goes up. In that case the tank gets set early and the rest follows later.

There is a middle path worth knowing about. A fiberglass or plastic tank can be moved and placed without the heavy equipment a concrete tank needs, which sometimes buys back the access problem entirely. Worth raising with your designer if the site is awkward.

The trade-off is real either way: going last protects the system but can hold up other parts of the job, since occupancy usually waits on septic.

Reviewed August 2026. Links go to the sources this answer was checked against.